1. FLOOR
1.1 |
Garage Floor
Power floated concrete. |
1.2 |
Office Floor
Reinforced concrete slab. |
1.3 |
Balconies
Reinforced concrete slab. |
2. WALLS
2.1 |
External Walls
230mm cement maxi brick cavity walls, plastered and painted with Acrylic PVA
externally. Internal skin to be plastered and finished with Acrylic PVA. |
2.2 |
Internal Dividing Walls
190mm cement maxi brick wall to underside of roof tiles / concrete floor slab,
plastered on both sides and finished with Acrylic PVA. |
2.3 |
Toilet Walls
90mm cement maxi brick to underside of concrete slab / into ceiling space,
plastered on both sides and finished with Acrylic PVA. |
2.4 |
Partitioning
25 linear metre of Rhino drywall partitioning per 100 square metre of rentable
floor space, including one semi – solid door per 10 linear meter
of partitioning. |
3. WINDOWS
Black epoxy coated aluminium entrance doors with fixed
glazing or aluminium opening sections as shown. Black epoxy
coated louvres to allow for future air conditioning units. All
to AAAMSA standards.
4. DOORS & DOOR FRAMES
4.1
|
Front Door and door frames
Black epoxy coated aluminium entrance doors with clear gazed sections to AAAMSA
standards.
|
4.2
|
Toilet and Kitchenette
Mild steel jamb lining and semi-solid door with embossed door facing, all finished
in gloss enamel.
|
4.3
|
Partition doors
Semi-solid door finished in gloss enamel.
|
4.4
|
Ironmongery
Cylinder locks and stainless steel handles to aluminium entrance and balcony
doors.
2 Lever lockset and chrome plated door handles to all internal doors.
|
5.
CEILING
5.1
|
Parking garage
Off/shutter concrete.
|
5.2
|
Foyer, kitchenette and WC’s
Suspended Donn screw up grid system with 9.5mm Gypsum Rhinoboard, skimmed and
finished with Acrylic PVA.
|
5.3
|
Offices
1200 x 600mm lay in ceiling tiles in Donn ceiling system.
|
6. ROOF
6.1
|
Saflok 700 zincalume sheet metal roofing.
|
7. RAINWATER GOODS
7.1
|
Gutters and downpipes
150 x 150mm seamless aluminium gutters and 110mm PVC downpipes.
Continuous aluminium box gutters at valleys.
|
8. ELECTRICAL AND TELEPHONE
8.1 |
Distribution board
Recessed single phase board, with 60A main switch and earth leakage unit. |
8.2 |
Metering
Supply to each unit measured individually. |
8.3 |
Switched socket outlets
One 16A standard socket outlet for every 10 square metre floor area, mounted
in three tier powerskirting on inside of external walls of the building. |
8.4 |
Lighting
- Garage: twin tube fluorescent corrosion proof ceiling lamps
- Offices: 1200 x 600mm Prismatic recessed triple tube fluorescent light fittings
in ceiling panels to provide a lighting level of 400 lux at working surface level.
One light switch per 100 square floor are mounted in standard flush boxes 1200mm
above floor level.
- Foyer: Ceiling lamps with low voltage downlighters under landings.
- Kitchen: Incandescent ceiling lamp.
- WC’s: Incandescent ceiling lamp. |
8.5 |
Air-conditioning
Air conditioning will be provided through a combination of console type a/c units
and split type a/c units, with average cooling capacity of 100w/m² for
office space only. |
8.6 |
Telephone
One incoming Telkom conduit and blank box per unit. |
8.7
|
General
All light switches, socket outlets and blank cover plates to be CBi or clipsal
2000 range.
|
9. SECURITY SYSTEM AND ACCESS CONTROL
9.1
|
Security system
Each unit will be supplied with an alarm starter kit comprising a control panel,
keypad, siren and three passive infra red motion detectors with a direct
telephonic link via purchaser’s Telkom line to be centralized off-site
monitoring control centre. Monthly monitoring charges will be for the account
of the individual purchasers.
|
9.2
|
Access control
A guarded boom and gate will be operated during working hours.
After hours access to tenants will be via remote control.
After hours visitors to contact tenants via Mircom system.
Each unit will be linked to a Mircom system at the entrance gate. Monthly costs
for the account of the Body Corporate to be divided pro rata between the purchasers.
An intercom system from the front door to each section will be installed at each
building.
|
10. PLUMBING
10.1 |
Toilet
Two close-coupled WC suites and cisterns for each unit Vitreous china wash hand
basin on wall hangers with basin set pillar taps for hot and cold water. |
10.2 |
Kitchenette
Single end bowl stainless steel sink with single tap hole sink mixer tap, mounted
on melamine cupboard with two open shelves above. |
10.3 |
Piping
All piping to be built in.
Bottle trap to basins, PVC ‘P’ trap to sink. |
10.4 |
Metering
Bulk water metering controlled by Body Corporate. |
11. DRAINAGE
Ventilated “closed” drainage system with
rodding eyes, overflow gulleys and stub stacks.
12. TILING
12.1
|
Entrance foyer
Ceramic floor tiles to foyer, stairs and landings as per sample.
|
12.2
|
WC’s
Ceramic floor tiles at an allowance of R60.00 per square metre.
Ceramic wall tiles to 1200mm height at an allowance of R55.00 per square metre,
with timber dado rail.
|
12.3
|
Balconies
Ceramic tiles to balconies as per sample.
|
12.4
|
Mirrors
450 x 600mm mirror above all wash hand basins.
|
13. CARPETS
Belgotex “Berber Point”, ‘Basket Weave”, “Diagonals
or ‘Pavilion” at an allowance of R65.00 / per m²
14. GLAZING
14.1
|
Toilet windows
4mm obscured glazing.
|
14.2
|
Front door and Balcony doors
6mm safety glazing or as prescribed by SABS.
|
14.3
|
Other
4mm clear float glass.
|
15. EXTERNAL WORK
15.1 |
Main Access and Distribution Roads
Paving as per Phase
I & II. |
15.2 |
Signage
Provision of signage, to Tenant Signage Guidelines. Directory signage only provided
by developer. |
15.3 |
Entrance lighting
Weatherproof fittings by Eurolux or equal approve at entrance door. |
15.4 |
Area lighting
Lamp posts with luminaries by Eurolux or equal approved. |
15.5 |
Security Fence
1800mm profiled palisade fence with brick panels in areas. |
|